Building Plan Approval under The Punjab Factory Rules, 1952

  • Comment Author

    Overview

    The employer has to get approved the proposed building plans prior to construction of the factory from the Directorate of Factories in accordance with the provisions of Section 6 of the Act and rule 3 - A,4, 5 and 6. If the premises is extended including plant and machinery, the proposed building plans of the extension will be got approved prior to construction. Acceptance of plans of new factory building is done within 30 days of time after receipt of complete Application / documents.


  • Comment Author

    Time Line(RTS TimeLine)

    Acceptance of plans of new factory extension in building/ amendment in building is done
    within 30 days of time as per RTS notification no. 5/27/2014 - 2GR - 2(PF)/668042/1 dated 15 - 01 - 2016
    ( Service No. 227 - 235) after receipt of complete Application / documents.


  • Comment Author

    Required documents

  • ≡ Undertaking.


    ≡ Form No. 1-C.


    ≡ Process Flow Chart.


    ≡ Form No.1-D.


    ≡ Form No.1-E.


    ≡ Form No.1-F(if required).


    ≡ C.A. Certificate(if required).


    ≡ Appointment letter of competent person.


    ≡ List of Machineries.


    ≡ Other Documents.



  • Comment Author

    Fees for the Approval of Building Plan

    “1% cess of deposite fee.”

After getting Building Plan Approval, an applicant can apply for following services:

Building Plan Services :

  • Service - I
    Proposed Building Plan.
  • Service - II
    Constructed Building Plan with Stability.
  • Service - III
    Existing Building Plan With Stability Certificate (Additions Building Plan).
  • Service - IV
    Existing Building Plan With Stability Certificate (Amendments Building Plan).
  • Service - V
    Only Stability Certificate.